Galiano Gold - Asanko Gold Mine Phase 1 Project Update
2014-6-18 Phase 1 of the Project is fully permitted for the commencement of construction. In early June, the Minerals Commission declared a moratorium over the expected mining and infrastructure areas.
More
$ASANKO$GOLD$MINE$
2016-7-18 asanko* This$ document$ has$ been$ prepared$ by$ Asanko$ Gold$ Inc.$ (the$ “Company”)$ solely$ for$ informaZonal$ purposes.$ This$ presentaZon$ is$ the$ sole$ responsibility$ of$
More
Asanko Gold Confirms Robust Economics for Phase 1
2014-11-13 The AGM consists of six known open pit deposits over a 30km trend and is being developed in two phases. Phase 1 will mine the Nkran pit, which accounts for 85% of the Phase 1 ore reserves, and four satellite deposits, Abore, Asuadai, Dynamite Hill and Adubiaso.
More
Asanko Gold Confirms Mineral Resources for Phase One
Asanko Gold Inc. (“Asanko” or the “Company”) (TSX:AKG)(NYSE MKT:AKG) is pleased to announce the Mineral Resource Estimate (“MRE”) for Phase 1 of the Asanko Gold Mine (“AGM” or the “Project”) in Ghana, including a maiden resource for the newly discovered Dynamite Hill deposit. This follows the decision by Asanko to do a comprehensive review of the original May 2012 MRE1 for ...
More
Asanko Gold Mine, Ghana - Mining Frontier
2020-1-11 Phase 1 of Asanko gold mine development consists of Nkran, Abore, Adubiaso, Dynamite Hill and Asuadai deposits, which are situated in the Asankrangwa Belt within the Kumasi Basin that hosts world-renowned gold mines, including AngloGold Ashanti’s Obuasi deposit.
More
Asanko Gold Mine Phase 1 Project Update - Yahoo
2014-6-18 VANCOUVER, BRITISH COLUMBIA--(Marketwired - Jun 18, 2014) - Asanko Gold Inc. ("Asanko" or the "Company") ()(NYSE MKT:AKG) is pleased to provide an update on activities at the fully funded and permitted Asanko Gold Mine (the "AGM" or the "Project") in Ghana.In early April, the Company engaged DRA as the Engineering, Procurement, Construction and Management ("EPCM") contractor for the design and ...
More
Asanko Gold Mine Phase 1 Project Update - Yahoo
2014-6-18 Asanko Gold Mine Phase 1 Project Update. VANCOUVER, BRITISH COLUMBIA-- (Marketwired - Jun 18, 2014) - Asanko Gold Inc. ("Asanko" or the "Company") ( AKG.TO ) (NYSE MKT:AKG) is pleased to provide ...
More
Galiano Gold - Operations - Asanko Gold Mine
Located in Ghana, West Africa, the Asanko Gold Mine is a joint venture with Gold Fields Ltd (JSE, NYSE: GFI). Galiano and Gold Fields both have a 45% economic interest in the mine, with the Government of Ghana holding the remaining 10%. Galiano is the manager and operator. The Asanko Gold Mine is a multi-deposit complex, with two main deposits ...
More
Asanko Gold: Resources Don't Add Up - 90% Downside ...
2016-7-1 Data Source: Asanko Gold Mine - Phase 1 Definitive Project Plan; Company Disclosures, table produced by author 5.2 Step 2: 2016 Guidance vs. the DPP - April 1st, 2016, to December 31st, 2016
More
Asanko Gold Mine, Ghana - Mining Frontier
2020-1-11 Asanko Gold Mine, Ghana. Asanko Gold Mine, situated in Ghana, one of the top ten gold producing countries, is Asanko Gold’s flagship project. The mine, with proven and probable reserves of 4.8 million ounces, is planned to be developed in two phases. Construction on the phase 1 development of the project started in August 2014.
More
Asanko Gold Confirms Mineral Resources for Phase One
Asanko Gold Inc. (“Asanko” or the “Company”) (TSX:AKG)(NYSE MKT:AKG) is pleased to announce the Mineral Resource Estimate (“MRE”) for Phase 1 of the Asanko Gold Mine (“AGM” or the “Project”) in Ghana, including a maiden resource for the newly discovered Dynamite Hill deposit. This follows the decision by Asanko to do a comprehensive review of the original May 2012 MRE1 for ...
More
Galiano Gold - Asanko Gold Mine Announces First Gold ...
2016-1-26 About Asanko Gold Inc. Asanko’s vision is to become a mid-tier gold mining company that maximizes value for all its stakeholders. The Company’s flagship project is the multi-million ounce Asanko Gold Mine located in Ghana, West Africa. The mine is being developed in phases. Phase 1 has been commissioned, with first gold produced in early Q1 ...
More
Asanko Commissioning Ghana Gold Mine E MJ
2020-4-8 Asanko Gold began commissioning Phase 1 of its Asanko gold mine in southwest Ghana in December, with expectations that first gold would be produced in January. The project is designed to produce 190,000 ounces per year (oz/y) of gold over a period of 12 years at steady-state operations.
More
Construction Begins at Asanko Gold Mine E MJ
2020-4-8 Asanko Phase 1 development is based on a definitive feasibility study (DFS) of the Obotan project published by PMI Gold in September 2012. The DFS targeted approximately 2.25 million oz of gold production over an 11.5-year mine life, based on open-pit, contractor mining and a
More
Asanko - Obotan gold mine project Report Wood Mackenzie
2021-5-19 The Asanko project was derived from the combination of two standalone (Obotan Esaase) projects. The Obotan deposit will be developed as Phase 1, while the Esaase deposit will be developed as Phase 2. Both deposits will be mined by open-pit methods. Ore from Esaase will be transported 27km by overland conveyor to a carbon in leach plant at Obotan.
More
Asanko Gold prepares to commission Ghana gold mine ...
Asanko Gold Inc. [AKG-TSX, NYSE MKT] provided a construction update on Phase I of the Asanko Gold Mine in Ghana, West Africa, which has been under construction since August 2014 and is now preparing for hot commissioning in December 2015. Phase I is a low cost, long life mine that will produce an average of 190,000 ounces of gold
More
An Independent Qualified Persons’ Report
2014-10-24 1) The cut-off grade used for Phase 1, the Obotan Project resources (Nkran, Adubiaso, Abore, Dynamite Hill Asuadai) was 0.8 g/t 2) The cut-off grade used for Phase 2, the Esaase Project (Esaase) resource was 0.6 g/t 3) Columns may not add up due to rounding 4) All figures are in metric tonnes
More
Galiano Gold - Phase 2 Expansion Plan for Asanko Gold Mine ...
2015-5-14 Asanko Gold Inc. (“Asanko” or the “Company”) (TSX:AKG)(NYSE MKT:AKG) is pleased to announce the results of the Phase 2 expansion Pre-Feasibility Study (“PFS”) which combines the Phase 1 Obotan project, currently under construction, with the Esaase project as Phase 2 of the Asanko Gold Mine (“AGM” or the “Project”) in Ghana. The expanded project delivers enhanced project ...
More
Galiano Gold - Asanko Gold Amends Debt Repayment Schedule ...
2016-5-19 The Company’s flagship project is the multi-million ounce Asanko Gold Mine located in Ghana, West Africa. The mine is being developed in phases. Phase 1 was built within budget and ahead of schedule, with gold production commencing in January 2016 and commercial production declared on April 1, 2016.
More
Asanko Gold Mine Announces First Gold Production
The Company's flagship project is the multi-million ounce Asanko Gold Mine located in Ghana, West Africa. The mine is being developed in phases. Phase 1 has been commissioned, with first gold ...
More
Asanko Gold commences gold production from mine in Ghana
2016-1-27 Asanko Gold has commenced its first gold production of about 400oz from phase one of its mine in Ghana. The first gold production from the Asanko gold mine follows the commencement of operations of the entire processing facility one month ahead of schedule.
More
Asanko - Obotan gold mine project Report Wood Mackenzie
2021-5-19 The Asanko project was derived from the combination of two standalone (Obotan Esaase) projects. The Obotan deposit will be developed as Phase 1, while the Esaase deposit will be developed as Phase 2. Both deposits will be mined by open-pit methods. Ore from Esaase will be transported 27km by overland conveyor to a carbon in leach plant at Obotan.
More
Asanko Commissioning Ghana Gold Mine E MJ
2020-4-8 Asanko Gold began commissioning Phase 1 of its Asanko gold mine in southwest Ghana in December, with expectations that first gold would be produced in January. The project is designed to produce 190,000 ounces per year (oz/y) of gold over a period of 12 years at steady-state operations.
More
Construction Begins at Asanko Gold Mine E MJ
2020-4-8 Asanko Phase 1 development is based on a definitive feasibility study (DFS) of the Obotan project published by PMI Gold in September 2012. The DFS targeted approximately 2.25 million oz of gold production over an 11.5-year mine life, based on open-pit, contractor mining and a
More
Asanko gold project on track to produce 1st gold in Q1, 2016
2015-9-20 Ghana – Construction on Asanko Gold’s Asanko gold project – Phase 1 – is nearing completion and will be a low cost, long life mine producing 190 000 oz of gold per annum at steady state, with the first gold pour on track for early Q1, 2016. The project continues to advance with three quarters of the overall project complete and around 2 400 employees and contractors on site, as at the ...
More
Asanko Gold Mine Construction Update - goldseiten
2014-11-6 Highlights: - Phase 1 construction project 12% complete overall and on track for first gold in Q1 2016 - Contractor activity ramping up with approximately 375 contractors on site - First concrete ...
More
Asanko Gold prepares to commission Ghana gold mine ...
Asanko Gold Inc. [AKG-TSX, NYSE MKT] provided a construction update on Phase I of the Asanko Gold Mine in Ghana, West Africa, which has been under construction since August 2014 and is now preparing for hot commissioning in December 2015. Phase I is a low cost, long life mine that will produce an average of 190,000 ounces of gold
More
Major Mines Projects Asanko Mine
10 years (as of Jan 1, 2019) The Company changed its name from Asanko Gold Inc. to Galiano Gold Inc., following approval of the name change by the Company’s shareholders at its Annual General and Special Meeting on April 30, 2020. Latest News. Galiano Gold Provides Miradani North Phase 3
More
Galiano Gold - Asanko Gold Amends Debt Repayment Schedule ...
2016-5-19 The Company’s flagship project is the multi-million ounce Asanko Gold Mine located in Ghana, West Africa. The mine is being developed in phases. Phase 1 was built within budget and ahead of schedule, with gold production commencing in January 2016 and commercial production declared on April 1, 2016.